How much Apple is raising prices on MacBook Air, Pro models

How much Apple is raising prices on MacBook Air, Pro models

March 3, 2026
Amazon says services in Middle East go offline due to drone strikes on data centers

Amazon says services in Middle East go offline due to drone strikes on data centers

March 3, 2026
Dow plunges 1,000 points as oil, gas prices surge after Iran orders Strait of Hormuz closure

Dow plunges 1,000 points as oil, gas prices surge after Iran orders Strait of Hormuz closure

March 3, 2026
US senator urges DOJ, FTC to probe soaring costs of watching NFL games on streamers

US senator urges DOJ, FTC to probe soaring costs of watching NFL games on streamers

March 3, 2026
AI giant Anthropic ‘philosopher’ Amanda Askell’s oddball blog posts surface after Trump blasts ‘leftwing nut jobs’

AI giant Anthropic ‘philosopher’ Amanda Askell’s oddball blog posts surface after Trump blasts ‘leftwing nut jobs’

March 3, 2026
Facebook X (Twitter) Instagram
The Financial News 247The Financial News 247
Demo
  • Home
  • News
  • Business
  • Finance
  • Companies
  • Investing
  • Markets
  • Lifestyle
  • Tech
  • More
    • Opinion
    • Climate
    • Web Stories
    • Spotlight
    • Press Release
The Financial News 247The Financial News 247
Home » New York wind farm construction can proceed after judge lifts Trump suspension

New York wind farm construction can proceed after judge lifts Trump suspension

By News RoomJanuary 16, 2026No Comments4 Mins Read
Facebook Twitter Pinterest LinkedIn WhatsApp Telegram Reddit Email Tumblr
New York wind farm construction can proceed after judge lifts Trump suspension
Share
Facebook Twitter LinkedIn Pinterest Email

Work on a major offshore wind project in New York can continue after a federal judge temporarily lifted the Trump administration’s suspension of the undertaking — finding that the project faced serious harm if the halt remained in place.

US District Judge Carl Nichols issued a preliminary injunction blocking enforcement of a Dec. 22 stop-work order from the Interior Department’s Bureau of Ocean Energy Management, which had cited national security concerns in halting construction of the offshore wind farm, known as Empire Wind.

The Thursday ruling clears the way for Equinor, the Norwegian energy company behind the project, to restart offshore construction after work was halted amid a broader administration review of five East Coast wind developments.

Construction equipment for the Empire Wind offshore project is seen off the coast of New York.

Nichols said Empire Wind had showed an injunction risked sinking the project completely.

The project’s backers “established on this record that losing access to specialized vessels that cannot be replaced in time to meet binding deadlines, will not just cause substantial financial loss, but it will threaten Empire Wind’s entire existence,” the judge stated.

“Damocles’s sword does not have to actually fall on the movant before the court will issue an injunction” in order to prevent irreparable harm,” he added.

President Trump, a Republican, has long blasted wind as “the worst form of energy,” seeking to slam the brakes on the sector while prioritizing oil, natural gas, coal, nuclear energy and more.

The Post has sought comment from the Interior Department.

“Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period,” the company said in a press release.

“In addition, the project will continue to engage with the US government to ensure the safe, secure and responsible execution of its operations.

A federal judge on Thursday allowed construction to resume on New York’s Empire Wind offshore wind project after temporarily blocking a suspension imposed by the Trump administration.

Gov. Kathy Hochul welcomed the judge’s decision — and slammed the feds’ rationale for issuing the stop-work order in the first place.

“They were stopped under the bogus pretense of national security,” the Dem said Thursday. “When I heard this, I said one thing, ‘I’m the Governor of New York. If there is a national security threat off the coast of New York, you need to tell me what it is — I want a briefing right now.’

“Lo and behold, they had no answer.”

Equinor is developing Empire Wind to supply renewable electricity to New York City.

Built in two phases, the big project is designed to generate more than 2,000 megawatts of power — enough to supply electricity to over 1 million homes.

The Empire Wind offshore wind project, located in federal waters of the Atlantic Ocean southeast of Long Island, is set to resume construction following a court ruling.

The first phase, Empire Wind 1, has a planned capacity of 810 megawatts and is about 60% complete.

Construction began in 2024, with all 54 monopile foundations — cylindrical structures jammed into the seafloor — installed in the federal waters of the Atlantic Ocean, roughly 15–20 miles southeast of Long Island.

The monopiles were driven into the seabed at the offshore project site, where the wind turbines will be mounted.

Onshore and near-shore work — including cable staging, port activity and grid-connection infrastructure — is taking place in and around New York Harbor and Brooklyn.

Work was halted in late December after federal officials ordered a stop to construction, pausing a critical phase involving installation of the project’s offshore electrical substation.

A federal stop-work order issued during the Trump administration’s push to pause offshore wind projects temporarily halted construction on Empire Wind.

Developers warned the delay risked derailing the project due to tight construction windows and limited availability of specialized vessels.

“President Trump has been clear: wind energy is the scam of the century,” White House spokeswoman Taylor Rogers told The Post.

“For years, Americans have been forced to pay billions more for the least reliable source of energy.”

“The Trump administration has paused the construction of all large-scale offshore wind projects,” Rogers added, “because our number one priority is to put America First and protect the national security of the American people. The Administration looks forward to ultimate victory on the issue.”

Business Energy Green Energy interior department offshore wind Renewable Energy
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

Related News

How much Apple is raising prices on MacBook Air, Pro models

How much Apple is raising prices on MacBook Air, Pro models

March 3, 2026
Amazon says services in Middle East go offline due to drone strikes on data centers

Amazon says services in Middle East go offline due to drone strikes on data centers

March 3, 2026
Dow plunges 1,000 points as oil, gas prices surge after Iran orders Strait of Hormuz closure

Dow plunges 1,000 points as oil, gas prices surge after Iran orders Strait of Hormuz closure

March 3, 2026
US senator urges DOJ, FTC to probe soaring costs of watching NFL games on streamers

US senator urges DOJ, FTC to probe soaring costs of watching NFL games on streamers

March 3, 2026
AI giant Anthropic ‘philosopher’ Amanda Askell’s oddball blog posts surface after Trump blasts ‘leftwing nut jobs’

AI giant Anthropic ‘philosopher’ Amanda Askell’s oddball blog posts surface after Trump blasts ‘leftwing nut jobs’

March 3, 2026
Xbox exec says she was pushed out after refusing to wear bathrobe at hotel

Xbox exec says she was pushed out after refusing to wear bathrobe at hotel

March 3, 2026
Add A Comment
Leave A Reply Cancel Reply

Don't Miss
Amazon says services in Middle East go offline due to drone strikes on data centers

Amazon says services in Middle East go offline due to drone strikes on data centers

Business March 3, 2026

Amazon said drone strikes significantly damaged two of its data centers and a facility in…

Dow plunges 1,000 points as oil, gas prices surge after Iran orders Strait of Hormuz closure

Dow plunges 1,000 points as oil, gas prices surge after Iran orders Strait of Hormuz closure

March 3, 2026
US senator urges DOJ, FTC to probe soaring costs of watching NFL games on streamers

US senator urges DOJ, FTC to probe soaring costs of watching NFL games on streamers

March 3, 2026
AI giant Anthropic ‘philosopher’ Amanda Askell’s oddball blog posts surface after Trump blasts ‘leftwing nut jobs’

AI giant Anthropic ‘philosopher’ Amanda Askell’s oddball blog posts surface after Trump blasts ‘leftwing nut jobs’

March 3, 2026
Stay In Touch
  • Facebook
  • Twitter
  • Pinterest
  • Instagram
  • YouTube
  • Vimeo
Our Picks

Data Plateau: Hit The Scaling Wall With AI Or Remain An Innovator?

March 3, 2026
Xbox exec says she was pushed out after refusing to wear bathrobe at hotel

Xbox exec says she was pushed out after refusing to wear bathrobe at hotel

March 3, 2026

When Claude Paused: An AI Doomsday Preview And The Question Of Human Survival

March 3, 2026
Elise Stefanik, Rick Scott demand probe into Chinese gadget maker Anker over spying fears: ‘Unacceptable risks’

Elise Stefanik, Rick Scott demand probe into Chinese gadget maker Anker over spying fears: ‘Unacceptable risks’

March 3, 2026
The Financial News 247
Facebook X (Twitter) Instagram Pinterest
  • Privacy Policy
  • Terms of use
  • Advertise
  • Contact us
© 2026 The Financial 247. All Rights Reserved.

Type above and press Enter to search. Press Esc to cancel.